Design/build svcs for KM Lakes Cell 1 Inflow & Outflow Spillways

Date Issued: 07/25/2016

Deadline: 08/26/2016  prior to 10:00 AM   M.D.T.

Requisition Number:

Delivery Point: Brighton, CO

Delivery Date: 03/31/2017

Type of Purchase: Term: Unspecified

Construction Related: Yes

Type of Response Allowed: Hard Copy Only

Issuing Agency: City of Brighton

Using Department: Utilities

Special Notices: All or None Award
Bid Bond Required
Contractors License Required
Disadvantaged Business Enterprise (DBE)
FOB Destination
Insurance Required
Labor and Materials Bond Required
Maintenance Bond Required
Minority Business Participation
No Brand Name Specified
Payment Terms = Net 30
Performance Bond Required
Women-Owned Business Participation
Onsite Visit Mandatory on 08/08/2016 10:00 AM at Post pre-bid
Prebid Conference Mandatory on 08/08/2016 10:00 AM at City Hall - 500 S. 4th Ave., Brighton, CO 80601

ACCEPTING VENDOR QUESTIONS:

Due Date: 8/15/2016 4:00:00 PM M.D.T.

Primary Contact Name: Mrs. Pamela L Roeding C.P.M

Title: Procurement and Contracts Manager

Email: proeding@brightonco.gov

SUMMARY OF SPECIFICATIONS:

The City is requesting formal proposals for a design-build team to design and construct two spillways based upon Urban Drainage standards. The design-build team shall provide all survey, environmental and geotechnical evaluation, civil design and construction necessary to complete a seamless, cost-effective, and timely project. The design-build team shall procure, or assist in procurement of, all applicable permits including, but not limited to, floodplain permits, environmental permits and assessments, 404 permits, and erosion and sediment control permits. Time is a critical component for this project. The City is requiring the project infrastructure be completed by March 31, 2017.  

SIMILAR BIDS FROM CITY OF BRIGHTON

DOCUMENT TITLES DOCUMENT NUMBER DEADLINE
South Platte Interceptor Interconnect Construction ITB-16-007R  7/18/2016 11:00:00 AM 
South Platte Interceptor Interconnect Construction ITB-16-007  4/18/2016 10:00:00 AM 
Cell 1 Rip Rap Construction ITB-16-008  4/11/2016 11:00:00 AM 
Non-Potable Connections Construction Project ITB-16-001  2/17/2016 10:00:00 AM 
Design/Build Services for Ken Mitchell Lakes Cell 1 Diversion RFP-15-052  12/7/2015 10:00:00 AM 
NORTH AND SOUTH TANK DRAINAGE ENGINEERING DESIGN RFP-15-049  10/14/2015 1:00:00 PM 
64 FARMSTEADS – HISTORIC SURVEYS PHASE 2 RFP-15-035-  9/10/2015 12:00:00 PM 
Greensand Plant Scaffolding Engineering Design RFP-15-044  9/10/2015 10:00:00 AM 
South Platte Reservoir’s Embankment Protection Designs RFP-15-045  9/9/2015 10:00:00 AM 
64 FARMSTEADS – HISTORIC SURVEYS PHASE 2 RFP-15-035 phase 2  8/11/2015 11:34:22 AM 

Get Automatic Notification and More


REGISTER

  • Real-time notification of solicitations, addenda and awards
  • Advance notice of term contract expirations
  • Full customer service support
  • Opportunities matched to your business
  • Access opportunities from all member agencies in one location