Design/Build Services for Ken Mitchell Lakes Cell 1 Diversion - City of Brighton RFP-15-052

City of Brighton » RFP-15-052

The information below is a summary of solicitation number RFP-15-052 posted by City of Brighton.  As a reminder, this solicitation is closed and responses are no longer being accepted.

Design/Build Services for Ken Mitchell Lakes Cell 1 Diversion

Date Issued: 11/05/2015

Deadline: 12/07/2015  prior to 10:00 AM   M.S.T.

Requisition Number:

Delivery Point: Brighton, CO

Delivery Date: May 15, 2016

Type of Purchase: Term: Unspecified

Construction Related: Yes

Type of Response Allowed: Hard Copy Only

Issuing Agency: City of Brighton

Using Department: Utilities Department

Special Notices: All or None Award
Bid Bond Required
Contractors License Required
FOB Destination
Insurance Required
Labor and Materials Bond Required
Maintenance Bond Required
Minority Business Participation
Payment Terms = Net 30
Performance Bond Required
Prevailing Wage Required
Small Business Participation
Women-Owned Business Participation
Onsite Visit Mandatory on 11/19/2015 12:00 PM at Start at City Hall, 500 S. 4th Avenue in Brighton
Prebid Conference Mandatory on 11/19/2015 10:00 AM at City Hall, 500 S. 4th Avenue, Brighton, CO

ACCEPTING VENDOR QUESTIONS:

Due Date: 11/30/2015 3:00:00 PM M.S.T.

Primary Contact Name: Mrs. Pamela L.  Roeding, CPM

Title: Procurement & Contracts Supervisor

Email: proeding@brightonco.gov

SUMMARY OF SPECIFICATIONS:

Ken Mitchell Cell 1 is a reservoir owned and operated by the City of Brighton. It is located on the west side of the City of Brighton along the South Platte River. A pump station was constructed in 2007 that can pump water from the river into the reservoir and back out of the reservoir into the river. These reservoir facilities sustained serious damage during flooding in June 2015. This damage resulted in an emergency declaration by the City on July 28th, 2015. During the event, the river changed course, almost completely submerging the diversion structure into Ken Mitchell Cell 1. The structure has settled and cracked, and the outflowing and inflowing concrete lines have been compromised. All cables for electricity and controls have been cut. Gates, actuators, and related components will need to be evaluated for potential salvage and reuse. While water level still prevents detailed investigation of the structure, it is clear that the diversion structure in its existing condition is not operational. The structures, including the concrete structure, electrical equipment, controls, and gates must be redesigned and reconstructed to take into account the new river bank locations and to improve on existing conditions that caused significant siltation within the diversion box itself prior to flooding. 

SIMILAR BIDS FROM CITY OF BRIGHTON

DOCUMENT TITLES DOCUMENT NUMBER DEADLINE
Design/build svcs for KM Lakes Cell 1 Inflow & Outflow Spillways RFP- 16-017  8/26/2016 10:00:00 AM 
South Platte Interceptor Interconnect Construction ITB-16-007R  7/18/2016 11:00:00 AM 
South Platte Interceptor Interconnect Construction ITB-16-007  4/18/2016 10:00:00 AM 
Cell 1 Rip Rap Construction ITB-16-008  4/11/2016 11:00:00 AM 
Non-Potable Connections Construction Project ITB-16-001  2/17/2016 10:00:00 AM 
Bromley-Hishinuma Farm Landscaping Phase 1 ITB-16-003  2/12/2016 2:00:00 PM 
Outdoor Warning Systems ITB-15-050-R  12/15/2015 10:00:00 AM 
Outdoor Warning Systems ITB-15-050  11/2/2015 10:00:00 AM 
NORTH AND SOUTH TANK DRAINAGE ENGINEERING DESIGN RFP-15-049  10/14/2015 1:00:00 PM 
Handicap Ramp Replacement Program (2015 CDBG Project) ITB-15-047  10/14/2015 11:00:00 AM 

Get Automatic Notification and More


REGISTER

  • Real-time notification of solicitations, addenda and awards
  • Advance notice of term contract expirations
  • Full customer service support
  • Opportunities matched to your business
  • Access opportunities from all member agencies in one location